# PMO Plugin Reference (projman-pmo)
|
||||
|
||||
## Overview
|
||||
|
||||
The `projman-pmo` plugin provides multi-project PMO coordination with cross-project dependency tracking, resource allocation, and company-wide visibility. It builds on projman but operates at the organization level.
|
||||
|
||||
**Build Order:** Build AFTER projman is working and validated
|
||||
**Target Users:** PMO coordinators, engineering managers, CTOs
|
||||
**Scope:** Multi-project coordination across entire organization
|
||||
|
||||
**Key Features:**
|
||||
- Cross-project status aggregation
|
||||
- Dependency tracking and visualization
|
||||
- Resource conflict detection
|
||||
- Release coordination
|
||||
- Company-wide lessons learned search
|
||||
- Multi-project prioritization
|
||||
|
||||
---
|
||||
|
||||
## Plugin Structure
|
||||
|
||||
```
|
||||
projman-pmo/
|
||||
├── .claude-plugin/
|
||||
│ └── plugin.json # Plugin manifest
|
||||
├── .mcp.json # Points to ../mcp-servers/ (company mode)
|
||||
├── commands/
|
||||
│ ├── pmo-status.md # Multi-project status overview
|
||||
│ ├── pmo-priorities.md # Cross-project prioritization
|
||||
│ ├── pmo-dependencies.md # Dependency visualization
|
||||
│ ├── pmo-conflicts.md # Resource conflict detection
|
||||
│ └── pmo-schedule.md # Deployment schedule coordination
|
||||
├── agents/
|
||||
│ └── pmo-coordinator.md # Multi-project coordination agent
|
||||
└── README.md # Installation and usage guide
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Configuration
|
||||
|
||||
### Plugin .mcp.json
|
||||
|
||||
**File:** `projman-pmo/.mcp.json`
|
||||
|
||||
```json
|
||||
{
|
||||
"mcpServers": {
|
||||
"gitea-pmo": {
|
||||
"command": "python",
|
||||
"args": ["-m", "mcp_server.server"],
|
||||
"cwd": "${CLAUDE_PLUGIN_ROOT}/../mcp-servers/gitea",
|
||||
"env": {
|
||||
"PYTHONPATH": "${CLAUDE_PLUGIN_ROOT}/../mcp-servers/gitea",
|
||||
"GITEA_API_URL": "${GITEA_API_URL}",
|
||||
"GITEA_API_TOKEN": "${GITEA_API_TOKEN}",
|
||||
"GITEA_OWNER": "${GITEA_OWNER}"
|
||||
}
|
||||
},
|
||||
"wikijs-pmo": {
|
||||
"command": "python",
|
||||
"args": ["-m", "mcp_server.server"],
|
||||
"cwd": "${CLAUDE_PLUGIN_ROOT}/../mcp-servers/wikijs",
|
||||
"env": {
|
||||
"PYTHONPATH": "${CLAUDE_PLUGIN_ROOT}/../mcp-servers/wikijs",
|
||||
"WIKIJS_API_URL": "${WIKIJS_API_URL}",
|
||||
"WIKIJS_API_TOKEN": "${WIKIJS_API_TOKEN}",
|
||||
"WIKIJS_BASE_PATH": "${WIKIJS_BASE_PATH}"
|
||||
}
|
||||
}
|
||||
}
|
||||
}
|
||||
```
|
||||
|
||||
**Critical Differences from projman:**
|
||||
- **NO** `GITEA_REPO` → operates on all repositories
|
||||
- **NO** `WIKIJS_PROJECT` → operates on entire `/hyper-hive-labs` namespace
|
||||
- Same shared MCP servers at `../mcp-servers/`
|
||||
|
||||
### Environment Variables
|
||||
|
||||
**Required (System-Level Only):**
|
||||
- `GITEA_API_URL`
|
||||
- `GITEA_API_TOKEN`
|
||||
- `GITEA_OWNER`
|
||||
- `WIKIJS_API_URL`
|
||||
- `WIKIJS_API_TOKEN`
|
||||
- `WIKIJS_BASE_PATH`
|
||||
|
||||
**NOT Required:**
|
||||
- `GITEA_REPO` - PMO operates across all repos
|
||||
- `WIKIJS_PROJECT` - PMO operates across entire namespace
|
||||
|
||||
---
|
||||
|
||||
## PMO Coordinator Agent
|
||||
|
||||
**File:** `agents/pmo-coordinator.md`
|
||||
|
||||
### Agent Personality
|
||||
|
||||
```markdown
|
||||
You are the PMO Coordinator for Hyper Hive Labs.
|
||||
|
||||
Your role:
|
||||
- Maintain strategic view across all projects
|
||||
- Identify cross-project dependencies
|
||||
- Detect resource conflicts
|
||||
- Balance competing priorities
|
||||
- Coordinate release timing
|
||||
- Track customer deployment schedules
|
||||
- Surface company-wide lessons learned
|
||||
|
||||
You are:
|
||||
- Strategic thinker
|
||||
- Dependency-aware
|
||||
- Conflict detector
|
||||
- Priority balancer
|
||||
- Team coordinator
|
||||
- NOT a micromanager
|
||||
|
||||
You delegate to project-level agents:
|
||||
- Don't micromanage single projects
|
||||
- Focus on cross-project issues
|
||||
- Surface conflicts early
|
||||
- Facilitate coordination
|
||||
- Provide strategic guidance
|
||||
|
||||
Available Tools:
|
||||
- aggregate_issues: Fetch issues across all repositories
|
||||
- search_all_projects: Search lessons across all projects
|
||||
- list_repos: Get all organization repositories
|
||||
- get_shared_docs: Access company-wide patterns and best practices
|
||||
|
||||
Key Principles:
|
||||
1. Strategic overview, not tactical details
|
||||
2. Cross-project coordination, not single-project management
|
||||
3. Identify conflicts before they become problems
|
||||
4. Balance competing priorities across teams
|
||||
5. Learn from patterns across all projects
|
||||
```
|
||||
|
||||
### Delegation Model
|
||||
|
||||
```
|
||||
PMO Agent (projman-pmo)
|
||||
├─ Identifies cross-project issues
|
||||
├─ Detects resource conflicts
|
||||
├─ Coordinates release timing
|
||||
└─ Delegates to...
|
||||
├─ Planner Agent (projman) → for project planning
|
||||
├─ Orchestrator Agent (projman) → for project execution
|
||||
└─ Executor Agent (projman) → for implementation
|
||||
```
|
||||
|
||||
**Example:**
|
||||
```
|
||||
User: /pmo-status
|
||||
|
||||
PMO: Projects Overview:
|
||||
|
||||
CuisineFlow: Sprint in progress, 60% complete
|
||||
└─ Blocking: CuisineFlow-Site deployment
|
||||
|
||||
I notice CuisineFlow-Site is waiting on API changes.
|
||||
Use projman in the cuisineflow-site repo to plan the sync work.
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Commands
|
||||
|
||||
### 1. PMO Status Command
|
||||
|
||||
**File:** `commands/pmo-status.md`
|
||||
|
||||
**Usage:** `/pmo-status`
|
||||
|
||||
**Description:** Consolidated view of all active projects
|
||||
|
||||
**Flow:**
|
||||
|
||||
```
|
||||
User: /pmo-status
|
||||
|
||||
PMO: Projects Overview
|
||||
================
|
||||
|
||||
CuisineFlow (main product)
|
||||
├── Sprint: Intuit Engine Extraction
|
||||
├── Status: In Progress (60%)
|
||||
├── Issue: #47
|
||||
├── Blockers: None
|
||||
├── Next: API testing
|
||||
└── Timeline: On track (1 week remaining)
|
||||
|
||||
CuisineFlow-Site (demo)
|
||||
├── Sprint: Dashboard Updates
|
||||
├── Status: Waiting on dependencies
|
||||
├── Issue: #12
|
||||
├── Blockers: Depends on CuisineFlow #47 (API changes)
|
||||
├── Next: Deploy when API ready
|
||||
└── Timeline: Blocked (waiting on CuisineFlow)
|
||||
|
||||
Intuit-Engine (service)
|
||||
├── Sprint: Initial Setup
|
||||
├── Status: Planning
|
||||
├── Issue: #3
|
||||
├── Blockers: Architecture decisions needed
|
||||
├── Next: Service boundary definition
|
||||
└── Timeline: Not started
|
||||
|
||||
HHL-Site (marketing)
|
||||
├── Sprint: Content Updates
|
||||
├── Status: Complete
|
||||
├── Issue: #8 (closed)
|
||||
├── Blockers: None
|
||||
├── Next: Deploy to production
|
||||
└── Timeline: Ready for deployment
|
||||
|
||||
Cross-Project Insights:
|
||||
- CuisineFlow-Site blocked by CuisineFlow #47
|
||||
- Intuit-Engine needs architectural guidance
|
||||
- HHL-Site ready for deployment
|
||||
|
||||
Suggested Actions:
|
||||
1. Prioritize CuisineFlow #47 completion (unblocks Site)
|
||||
2. Schedule architecture review for Intuit-Engine
|
||||
3. Deploy HHL-Site content updates
|
||||
```
|
||||
|
||||
**Success Criteria:**
|
||||
- Shows all active projects
|
||||
- Identifies blockers
|
||||
- Surfaces dependencies
|
||||
- Provides actionable insights
|
||||
|
||||
### 2. PMO Priorities Command
|
||||
|
||||
**File:** `commands/pmo-priorities.md`
|
||||
|
||||
**Usage:** `/pmo-priorities`
|
||||
|
||||
**Description:** Review and adjust priorities across projects
|
||||
|
||||
**Flow:**
|
||||
|
||||
```
|
||||
User: /pmo-priorities
|
||||
|
||||
PMO: Priority Analysis Across Projects
|
||||
=================================
|
||||
|
||||
Critical (Blocks launches):
|
||||
1. CuisineFlow #47 - Intuit Engine Extraction
|
||||
→ Blocks: CuisineFlow v2.0 launch (Nov 15)
|
||||
→ Blocks: CuisineFlow-Site deployment
|
||||
→ Status: 60% complete, 1 week remaining
|
||||
→ Recommendation: Maintain focus
|
||||
|
||||
High (Important features):
|
||||
2. CuisineFlow-Site #12 - Dashboard Updates
|
||||
→ Depends on: CuisineFlow #47
|
||||
→ Status: Waiting
|
||||
→ Recommendation: Begin planning, wait for #47
|
||||
|
||||
3. Intuit-Engine #3 - Initial Setup
|
||||
→ Enables: Service architecture
|
||||
→ Status: Planning phase
|
||||
→ Recommendation: Schedule architecture review
|
||||
|
||||
Medium (Enhancements):
|
||||
4. HHL-Site #8 - Content Updates
|
||||
→ Status: Complete, ready to deploy
|
||||
→ Recommendation: Deploy this week
|
||||
|
||||
Resource Analysis:
|
||||
Leo (primary developer):
|
||||
- Working on: CuisineFlow #47 (Critical)
|
||||
- Next: CuisineFlow-Site #12 (High)
|
||||
- Later: Intuit-Engine #3 (High)
|
||||
|
||||
⚠️ Potential Conflict:
|
||||
Leo is assigned to 3 high-priority items. Consider:
|
||||
- Maintaining focus on #47 (blocks launch)
|
||||
- Queueing #12 for after #47 completion
|
||||
- Scheduling #3 architecture review with team
|
||||
|
||||
Recommend any priority changes?
|
||||
```
|
||||
|
||||
**Success Criteria:**
|
||||
- Clear priority ranking
|
||||
- Resource allocation visibility
|
||||
- Conflict identification
|
||||
- Actionable recommendations
|
||||
|
||||
### 3. PMO Dependencies Command
|
||||
|
||||
**File:** `commands/pmo-dependencies.md`
|
||||
|
||||
**Usage:** `/pmo-dependencies`
|
||||
|
||||
**Description:** Visualize and manage project dependencies
|
||||
|
||||
**Flow:**
|
||||
|
||||
```
|
||||
User: /pmo-dependencies
|
||||
|
||||
PMO: Project Dependencies
|
||||
====================
|
||||
|
||||
Dependency Graph:
|
||||
|
||||
Intuit-Engine (service)
|
||||
↓ (must complete before)
|
||||
CuisineFlow (main)
|
||||
↓ (API changes required by)
|
||||
CuisineFlow-Site (demo)
|
||||
↓ (deploy together)
|
||||
Customer VPS (deployments)
|
||||
|
||||
Detailed Dependencies:
|
||||
|
||||
1. CuisineFlow → Intuit-Engine
|
||||
Type: Service extraction
|
||||
Status: In progress
|
||||
Blocker: Must complete #47 before v2.0 launch
|
||||
Impact: High (blocks launch)
|
||||
|
||||
2. CuisineFlow → CuisineFlow-Site
|
||||
Type: Feature sync
|
||||
Status: Waiting
|
||||
Blocker: Dashboard updates need API changes from #47
|
||||
Impact: Medium (demo consistency)
|
||||
|
||||
3. CuisineFlow → Customer VPS
|
||||
Type: Deployment
|
||||
Status: Pending
|
||||
Blocker: v2.0 launch must complete before customer updates
|
||||
Impact: High (customer commitments)
|
||||
|
||||
Deployment Order:
|
||||
1. Complete Intuit-Engine service extraction
|
||||
2. Deploy CuisineFlow v2.0 to production
|
||||
3. Sync CuisineFlow-Site demo
|
||||
4. Update customer VPS instances
|
||||
|
||||
Critical Path:
|
||||
Intuit-Engine (#3) → CuisineFlow (#47) → Site (#12) → Customer VPS
|
||||
Estimated timeline: 3 weeks total
|
||||
|
||||
Risks:
|
||||
- CuisineFlow #47 delay would cascade to all downstream
|
||||
- Customer VPS updates have Nov 20 deadline
|
||||
```
|
||||
|
||||
**Success Criteria:**
|
||||
- Dependencies clearly visualized
|
||||
- Critical path identified
|
||||
- Deployment order defined
|
||||
- Risks highlighted
|
||||
|
||||
### 4. PMO Conflicts Command
|
||||
|
||||
**File:** `commands/pmo-conflicts.md`
|
||||
|
||||
**Usage:** `/pmo-conflicts`
|
||||
|
||||
**Description:** Detect and resolve resource conflicts
|
||||
|
||||
**Flow:**
|
||||
|
||||
```
|
||||
User: /pmo-conflicts
|
||||
|
||||
PMO: Resource Conflict Analysis
|
||||
==========================
|
||||
|
||||
⚠️ Resource Conflict Detected
|
||||
|
||||
Leo (Developer):
|
||||
Assigned to:
|
||||
- CuisineFlow #47: Intuit Engine extraction (Priority: Critical)
|
||||
- CuisineFlow-Site #12: Dashboard redesign (Priority: High)
|
||||
- HHL-Site #8: Content update (Priority: Medium)
|
||||
- Intuit-Engine #3: Service setup (Priority: High)
|
||||
|
||||
Conflict Analysis:
|
||||
- 4 active assignments across 3 projects
|
||||
- 2 are high priority or above
|
||||
- Estimated total effort: 4 weeks
|
||||
- Timeline: 2 weeks available
|
||||
|
||||
Recommendations:
|
||||
1. FOCUS: CuisineFlow #47 (Critical, blocks launch)
|
||||
→ Keep as primary focus
|
||||
→ Estimated completion: 1 week
|
||||
|
||||
2. QUEUE: CuisineFlow-Site #12 (High, depends on #47)
|
||||
→ Start after #47 completes
|
||||
→ Natural sequencing
|
||||
|
||||
3. DELEGATE: HHL-Site #8 (Medium, content work)
|
||||
→ Can be handled by marketing team
|
||||
→ Low technical complexity
|
||||
|
||||
4. SCHEDULE: Intuit-Engine #3 (High, planning phase)
|
||||
→ Schedule architecture review session
|
||||
→ Team collaboration, not solo work
|
||||
|
||||
Timeline Conflict:
|
||||
|
||||
Without changes:
|
||||
Week 1-2: CuisineFlow #47
|
||||
Week 3-4: Site #12 + Engine #3 (CONFLICT)
|
||||
|
||||
With recommendations:
|
||||
Week 1-2: CuisineFlow #47 (FOCUS)
|
||||
Week 3: CuisineFlow-Site #12 (QUEUE)
|
||||
Week 4: Intuit-Engine #3 (SCHEDULE)
|
||||
HHL-Site #8: Marketing (DELEGATE)
|
||||
|
||||
Apply recommendations?
|
||||
```
|
||||
|
||||
**Success Criteria:**
|
||||
- Conflicts identified automatically
|
||||
- Clear impact analysis
|
||||
- Actionable recommendations
|
||||
- Timeline visualization
|
||||
|
||||
### 5. PMO Schedule Command
|
||||
|
||||
**File:** `commands/pmo-schedule.md`
|
||||
|
||||
**Usage:** `/pmo-schedule`
|
||||
|
||||
**Description:** Coordinate deployment schedules
|
||||
|
||||
**Flow:**
|
||||
|
||||
```
|
||||
User: /pmo-schedule
|
||||
|
||||
PMO: Deployment Schedule
|
||||
===================
|
||||
|
||||
Week of Nov 6:
|
||||
- CuisineFlow: Continue Sprint #47 (Intuit Engine)
|
||||
- HHL-Site: Deploy content updates (#8) ✅
|
||||
|
||||
Week of Nov 13:
|
||||
- CuisineFlow: Complete Sprint #47 ⚠️
|
||||
→ Critical: Must complete by Nov 15 for launch
|
||||
- CuisineFlow-Site: Begin Dashboard updates (#12)
|
||||
|
||||
Week of Nov 20:
|
||||
- CuisineFlow: Deploy v2.0 to production 🚀
|
||||
→ Deployment window: Nov 20-22
|
||||
- CuisineFlow-Site: Sync demo with v2.0
|
||||
- Customer VPS: Begin rollout (Deadline: Nov 20)
|
||||
|
||||
Week of Nov 27:
|
||||
- Customer VPS: Continue rollout
|
||||
- Intuit-Engine: Begin service implementation (#3)
|
||||
|
||||
Critical Dates:
|
||||
- Nov 15: CuisineFlow v2.0 feature freeze
|
||||
- Nov 20: Production deployment
|
||||
- Nov 20: Customer VPS deadline
|
||||
- Nov 22: Demo site sync
|
||||
|
||||
Dependencies:
|
||||
✅ Intuit-Engine service boundaries defined
|
||||
🔄 CuisineFlow #47 in progress (60%)
|
||||
⏳ CuisineFlow-Site #12 waiting
|
||||
⏳ Customer VPS rollout pending
|
||||
|
||||
Risks:
|
||||
⚠️ CuisineFlow #47 delay would impact:
|
||||
- v2.0 launch date (Nov 20)
|
||||
- Customer VPS deadline (Nov 20)
|
||||
- Demo site sync (Nov 22)
|
||||
|
||||
Mitigation:
|
||||
- Monitor #47 progress daily
|
||||
- Prepare rollback plan for customer VPS
|
||||
- Communicate delays early if detected
|
||||
```
|
||||
|
||||
**Success Criteria:**
|
||||
- Clear timeline visibility
|
||||
- Dependencies tracked
|
||||
- Critical dates highlighted
|
||||
- Risk mitigation planned
|
||||
|
||||
---
|
||||
|
||||
## Multi-Project Coordination Workflows
|
||||
|
||||
### Cross-Project Lessons Learned
|
||||
|
||||
```
|
||||
User: Search for lessons about service extraction across all projects
|
||||
|
||||
PMO: Searching lessons across all projects...
|
||||
|
||||
Found 5 relevant lessons:
|
||||
|
||||
CuisineFlow:
|
||||
- Sprint 08: Service boundary issues with shared DB
|
||||
Tags: #service-extraction #database #refactoring
|
||||
Key: Define boundaries at data model level first
|
||||
|
||||
- Sprint 12: API versioning during extraction
|
||||
Tags: #api #versioning #refactoring
|
||||
Key: Version APIs from the start
|
||||
|
||||
Intuit-Engine:
|
||||
- Sprint 02: Circular dependencies in service init
|
||||
Tags: #service-extraction #dependencies
|
||||
Key: Watch for import cycles
|
||||
|
||||
CuisineFlow-Site:
|
||||
- Sprint 05: Sync issues during backend refactor
|
||||
Tags: #sync #refactoring
|
||||
Key: Coordinate deployments during major changes
|
||||
|
||||
Shared Patterns:
|
||||
- /hyper-hive-labs/shared/architecture-patterns/service-extraction
|
||||
Key: Service Extraction Playbook
|
||||
|
||||
Common Themes:
|
||||
1. Data model boundaries are critical
|
||||
2. API versioning prevents integration issues
|
||||
3. Watch for circular dependencies
|
||||
4. Coordinate deployments during refactors
|
||||
|
||||
Apply these insights to current Intuit Engine extraction?
|
||||
```
|
||||
|
||||
### Resource Allocation
|
||||
|
||||
```
|
||||
User: /pmo-status
|
||||
|
||||
PMO: [Shows status]
|
||||
|
||||
Resource Analysis:
|
||||
- Leo: 3 active projects (CuisineFlow, Site, Engine)
|
||||
- Marketing: 1 project (HHL-Site)
|
||||
|
||||
Bottleneck detected: Leo is on critical path for all technical work
|
||||
|
||||
Recommendations:
|
||||
1. Prioritize work that unblocks others
|
||||
2. Consider hiring/contracting for parallel work
|
||||
3. Delegate non-critical work (HHL-Site content)
|
||||
|
||||
Would you like a detailed resource allocation report?
|
||||
```
|
||||
|
||||
### Release Coordination
|
||||
|
||||
```
|
||||
User: Plan the v2.0 release across all affected projects
|
||||
|
||||
PMO: Release Coordination: CuisineFlow v2.0
|
||||
======================================
|
||||
|
||||
Affected Projects:
|
||||
1. CuisineFlow (main product)
|
||||
2. Intuit-Engine (new service)
|
||||
3. CuisineFlow-Site (demo)
|
||||
4. Customer VPS instances
|
||||
|
||||
Pre-Release Checklist:
|
||||
✅ Intuit-Engine service deployed
|
||||
🔄 CuisineFlow #47 complete (60%)
|
||||
⏳ Integration tests pending
|
||||
⏳ Demo site updates pending
|
||||
⏳ Customer migration scripts ready
|
||||
|
||||
Deployment Sequence:
|
||||
1. Deploy Intuit-Engine service (backend)
|
||||
→ Date: Nov 18
|
||||
→ Duration: 2 hours
|
||||
→ Rollback plan: Ready
|
||||
|
||||
2. Deploy CuisineFlow v2.0 (main app)
|
||||
→ Date: Nov 20
|
||||
→ Duration: 4 hours
|
||||
→ Rollback plan: Ready
|
||||
|
||||
3. Sync CuisineFlow-Site (demo)
|
||||
→ Date: Nov 22
|
||||
→ Duration: 1 hour
|
||||
→ Dependencies: Step 2 complete
|
||||
|
||||
4. Update Customer VPS (production instances)
|
||||
→ Date: Nov 23-25
|
||||
→ Duration: Phased rollout
|
||||
→ Dependencies: Steps 2 and 3 complete
|
||||
|
||||
Communication Plan:
|
||||
- Nov 15: Feature freeze announcement
|
||||
- Nov 19: Deployment notification
|
||||
- Nov 20: v2.0 launch announcement
|
||||
- Nov 25: Completion report
|
||||
|
||||
Risks & Mitigation:
|
||||
- Risk: #47 completion delayed
|
||||
Mitigation: Daily progress checks, adjust timeline early
|
||||
|
||||
- Risk: Integration issues during deployment
|
||||
Mitigation: Comprehensive testing, rollback plan ready
|
||||
|
||||
- Risk: Customer VPS migration issues
|
||||
Mitigation: Phased rollout, support on standby
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Company-Wide Patterns
|
||||
|
||||
### Accessing Shared Documentation
|
||||
|
||||
```python
|
||||
# PMO agent can access company-wide patterns
|
||||
shared_patterns = await wikijs.get_shared_docs("architecture-patterns")
|
||||
|
||||
# Returns:
|
||||
# - microservices.md
|
||||
# - api-gateway.md
|
||||
# - database-per-service.md
|
||||
# - service-extraction.md (created from lessons learned)
|
||||
```
|
||||
|
||||
### Creating Shared Patterns
|
||||
|
||||
```
|
||||
User: Create a shared pattern document for service extraction
|
||||
|
||||
PMO: I'll create a pattern document based on lessons from:
|
||||
- CuisineFlow Sprint 08
|
||||
- CuisineFlow Sprint 12
|
||||
- Intuit-Engine Sprint 02
|
||||
|
||||
Creating: /hyper-hive-labs/shared/architecture-patterns/service-extraction
|
||||
|
||||
Service Extraction Pattern
|
||||
=========================
|
||||
|
||||
## When to Use
|
||||
- Extracting microservice from monolith
|
||||
- Creating separate deployable service
|
||||
- Isolating domain boundaries
|
||||
|
||||
## Prerequisites
|
||||
- Clear service boundaries defined
|
||||
- Data model dependencies mapped
|
||||
- API contracts specified
|
||||
|
||||
## Steps
|
||||
1. Define service boundaries at data model level
|
||||
2. Design and version APIs first
|
||||
3. Extract data layer with foreign key awareness
|
||||
4. Implement service logic
|
||||
5. Update integration points
|
||||
6. Deploy and test
|
||||
|
||||
## Common Pitfalls
|
||||
- Not defining boundaries at data level first
|
||||
- Missing API versioning
|
||||
- Circular dependencies in initialization
|
||||
- Uncoordinated deployments
|
||||
|
||||
## Lessons Learned
|
||||
[Links to specific sprint lessons]
|
||||
|
||||
Created ✅
|
||||
Tags: #service-extraction #microservices #refactoring #architecture
|
||||
|
||||
This pattern is now available to all projects.
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Implementation Phases
|
||||
|
||||
### Phase 9: PMO Plugin Foundation
|
||||
|
||||
**Deliverable:** PMO plugin requirements and design
|
||||
|
||||
**Tasks:**
|
||||
1. Analyze multi-project workflows
|
||||
2. Identify coordination pain points
|
||||
3. Design PMO agent scope
|
||||
4. Extend MCP server for multi-repo operations
|
||||
5. Define delegation model
|
||||
|
||||
**Success Criteria:**
|
||||
- Clear PMO plugin scope
|
||||
- Multi-repo queries working
|
||||
- Delegation model defined
|
||||
- Doesn't duplicate projman functionality
|
||||
|
||||
### Phase 10: PMO Commands & Workflows
|
||||
|
||||
**Deliverable:** PMO-specific commands working
|
||||
|
||||
**Tasks:**
|
||||
1. Implement `/pmo-status` command
|
||||
2. Implement `/pmo-priorities` command
|
||||
3. Implement `/pmo-dependencies` command
|
||||
4. Implement `/pmo-conflicts` command
|
||||
5. Implement `/pmo-schedule` command
|
||||
6. Build conflict detection logic
|
||||
7. Create dependency visualization
|
||||
8. Design release coordination workflow
|
||||
|
||||
**Success Criteria:**
|
||||
- All commands provide valuable insights
|
||||
- Dependencies clearly visualized
|
||||
- Conflicts easily identified
|
||||
- Coordination reduces manual overhead
|
||||
|
||||
### Phase 11: PMO Testing & Integration
|
||||
|
||||
**Deliverable:** Validated PMO plugin integrated with projman
|
||||
|
||||
**Tasks:**
|
||||
1. Test with multiple projects (CuisineFlow, Site, Engine, HHL-Site)
|
||||
2. Simulate deployment coordination scenarios
|
||||
3. Test priority conflict resolution
|
||||
4. Validate dependency tracking
|
||||
5. Test cross-project lessons search
|
||||
6. Ensure PMO delegates to projman agents
|
||||
|
||||
**Success Criteria:**
|
||||
- Handles multiple projects correctly
|
||||
- Dependencies respected
|
||||
- Conflicts detected and surfaced
|
||||
- Seamless integration with projman
|
||||
- Cross-project lessons accessible
|
||||
|
||||
### Phase 12: Production Deployment
|
||||
|
||||
**Deliverable:** PMO plugin deployed and operational
|
||||
|
||||
**Tasks:**
|
||||
1. Deploy across all environments (laptop, staging, production)
|
||||
2. Configure for company-wide access
|
||||
3. Set up backup and recovery
|
||||
4. Establish monitoring and maintenance
|
||||
5. Train team on PMO capabilities
|
||||
|
||||
**Success Criteria:**
|
||||
- Works in all environments
|
||||
- Configuration portable
|
||||
- Backup procedures documented
|
||||
- Team trained and comfortable
|
||||
|
||||
---
|
||||
|
||||
## PMO vs Projman: Key Differences
|
||||
|
||||
| Aspect | projman | projman-pmo |
|
||||
|--------|---------|-------------|
|
||||
| **Scope** | Single repository | All repositories |
|
||||
| **Configuration** | `GITEA_REPO` + `WIKIJS_PROJECT` | Neither (company-wide) |
|
||||
| **Agents** | Planner, Orchestrator, Executor | PMO Coordinator |
|
||||
| **Commands** | Sprint-focused | Cross-project coordination |
|
||||
| **Gitea Access** | Single repo issues | All repos issues |
|
||||
| **Wiki.js Access** | Project path | Entire namespace |
|
||||
| **Primary User** | Developer, Team Lead | PMO, Manager, CTO |
|
||||
| **Focus** | Tactical execution | Strategic coordination |
|
||||
| **Delegation** | N/A | Delegates to projman |
|
||||
|
||||
---
|
||||
|
||||
## Usage Examples
|
||||
|
||||
### Example 1: Detecting Blocked Work
|
||||
|
||||
```
|
||||
User: /pmo-status
|
||||
|
||||
PMO: CuisineFlow-Site: Waiting on dependencies
|
||||
Blocked by: CuisineFlow #47 (API changes)
|
||||
|
||||
Recommendation: Focus resources on CuisineFlow #47 to unblock Site work
|
||||
```
|
||||
|
||||
### Example 2: Resource Conflict Resolution
|
||||
|
||||
```
|
||||
User: /pmo-conflicts
|
||||
|
||||
PMO: Leo assigned to 4 tasks across 3 projects
|
||||
Estimated: 4 weeks work in 2 weeks timeline
|
||||
|
||||
Recommendations:
|
||||
- Maintain focus on Critical priority (CuisineFlow #47)
|
||||
- Delegate content work (HHL-Site #8) to marketing
|
||||
- Schedule architectural review (Intuit-Engine #3) as team session
|
||||
```
|
||||
|
||||
### Example 3: Release Planning
|
||||
|
||||
```
|
||||
User: /pmo-schedule
|
||||
|
||||
PMO: Critical Path: Engine → CuisineFlow → Site → Customer VPS
|
||||
Deadline: Nov 20 (Customer VPS commitment)
|
||||
|
||||
Current: Week 1 of 3
|
||||
Status: On track
|
||||
|
||||
Risk: If CuisineFlow #47 delayed, entire timeline at risk
|
||||
Mitigation: Daily progress monitoring
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Best Practices
|
||||
|
||||
### 1. Use PMO for Strategic View
|
||||
|
||||
- Don't micromanage individual projects
|
||||
- Focus on cross-project issues
|
||||
- Identify blockers and dependencies
|
||||
- Balance competing priorities
|
||||
|
||||
### 2. Delegate to Projman
|
||||
|
||||
- Use projman for project-specific planning
|
||||
- Let project teams handle tactical execution
|
||||
- PMO provides coordination, not implementation
|
||||
|
||||
### 3. Monitor Critical Path
|
||||
|
||||
- Identify which work blocks others
|
||||
- Focus resources on critical path items
|
||||
- Communicate delays early
|
||||
|
||||
### 4. Learn Across Projects
|
||||
|
||||
- Search lessons across all projects
|
||||
- Create shared patterns from common themes
|
||||
- Build company-wide knowledge base
|
||||
|
||||
### 5. Coordinate Releases
|
||||
|
||||
- Plan deployments across dependent projects
|
||||
- Communicate timelines clearly
|
||||
- Have rollback plans ready
|
||||
|
||||
---
|
||||
|
||||
## Troubleshooting
|
||||
|
||||
### Issue: PMO showing wrong mode
|
||||
|
||||
**Solution:**
|
||||
```bash
|
||||
# Ensure GITEA_REPO and WIKIJS_PROJECT are NOT set
|
||||
env | grep GITEA
|
||||
env | grep WIKIJS
|
||||
|
||||
# Should only show:
|
||||
# GITEA_API_URL, GITEA_API_TOKEN, GITEA_OWNER
|
||||
# WIKIJS_API_URL, WIKIJS_API_TOKEN, WIKIJS_BASE_PATH
|
||||
```
|
||||
|
||||
### Issue: Can't access all repositories
|
||||
|
||||
**Solution:**
|
||||
- Verify API token has organization-level access
|
||||
- Check token permissions in Gitea
|
||||
- Ensure GITEA_OWNER is correct
|
||||
|
||||
### Issue: Cross-project search not working
|
||||
|
||||
**Solution:**
|
||||
- Verify Wiki.js structure exists
|
||||
- Check base path is correct
|
||||
- Ensure projects have lessons-learned directories
|
||||
|
||||
---
|
||||
|
||||
## Next Steps
|
||||
|
||||
1. **Complete projman plugin** (Phases 1-8)
|
||||
2. **Validate projman works** with real sprints
|
||||
3. **Begin PMO foundation** (Phase 9)
|
||||
4. **Implement PMO commands** (Phase 10)
|
||||
5. **Test with multiple projects** (Phase 11)
|
||||
6. **Deploy to production** (Phase 12)
|
||||